Works in the scheme
Progress report to be published
Percentage completion and dated site photographs for each item will be published here and updated regularly.
- Roads and streets — concrete paving to LG&RD / TMA standards
- Sewerage — house connections, street sewers and link to Diyal Road trunk sewer
- Electricity and street lights — to be maintained by the owners (TMA condition i)
- Mosque — on the designated mosque plot
Under condition (iii) of the TMA approval, remaining development works are to be completed within two years of 30 September 2024.
Timeline
- Non-flood area report, Rod Kohi Irrigation
- Right-of-way NOC, C&W Highways
- Agriculture NOC
- General Environmental Assessment filed with EPA
- EPA environmental approval (construction phase)
- Scrutiny committee recommendation, DC Office D.I. Khan
- Mutation 24259: streets, road and solid-waste site transferred to TMA
- Scheme approved — TMA Approval No. 1716/TMA/DIK
- Completion period for remaining development works under TMA condition (iii)